Volvo Lipscomb Canterbury

October 2019

Week 32 of our Volvo Canterbury site can see the ceilings and lighting nearing completion.

First fix mechanical and electrical schemes are complete and showroom tiling is coming along nicely!

Externally, cladding to the main building and workshop is now in place and the partitions internally are continuing to pop-up thanks to our amazing fit-out team.